Q. Use the table provided to answer the following questions: Which activities are on the critical path? What is the duration of the Project? Which

Q. Use the table provided to answer the following questions:

Which activities are on the critical path?

What is the duration of the Project?

Which activity has the most start slack?

*Assume zero as early start (ES) time for activities A, B, C

Activity IDPredecessorTimeA*None8B*None4C*None7DB5EA, D4FC, D3GE2HE3IF5JH, I2KG, J3Answer 4 8A1 E 4 D5B4 2 F 3H 3 0(dummy) C7 5 G28 6 K 3 9 3 I 5 7 J 2 One way the critical path can be determined is by identifying all paths and calculate theirduration. As shown below,…